Get the latest tech news
US Regulator Rejects Bid To Boost Nuclear Power To Amazon Data Center
The Federal Energy Regulatory Commission (FERC) blocked Amazon's bid to access more power from the Susquehanna nuclear plant for its Pennsylvania data center, citing grid reliability and consumer cost concerns. The Hill reports: In a 2-1 decision, the FERC found the regional grid operator, PJM Inte...
The Federal Energy Regulatory Commission (FERC) blocked Amazon's bid to access more power from the Susquehanna nuclear plant for its Pennsylvania data center, citing grid reliability and consumer cost concerns. The Hill reports: In a 2-1 decision, the FERC found the regional grid operator, PJM Interconnection, failed to prove that the changes to the transmission agreement with Susquehanna power plant were necessary. In a dissenting statement, Phillips argued the deal with Amazon "represents a 'first of its kind' co-located load configuration" and that Friday's decision is a "step backward for both electric reliability and national security."